Installation of paddle dryer

1. Equipment inspection: Before installation, carefully check all parts of the dryer to ensure that the equipment is intact and clean the inside.
2. Foundation installation: Perform foundation installation of the equipment to ensure that the equipment is firmly installed on the ground. Use appropriate bolts and expansion nuts to tighten the base of the equipment.
3. Electrical connection: Connect the power line of the equipment to ensure that the electrical system is connected correctly. Check the junction box of the electrical equipment to ensure that all cables are firmly connected.
4. Transmission system debugging: Debug the transmission system, including motors, belts, gearboxes, etc. Check the lubrication of the transmission parts to ensure sufficient lubricating oil.
5. Cooling system debugging: Debug the cooling system of the equipment to ensure sufficient supply of cooling water. Check the cooler, fan, etc. to ensure that the equipment can effectively dissipate heat during operation.
6. Trial operation: Perform trial operation of the equipment and observe the operation of the equipment. Check for abnormal noise, vibration, etc. to ensure that the equipment is normal during the trial operation stage.